Sprint 2 · Estimation

How much would one slice take?

Live Parking Monitoring sized with function points and story points, then reconciled into a dated hour, cost, and calendar range.

Estimation appendix summary

The team estimated the Live Parking Monitoring slice (six backlog stories, 32 story points). Scope includes nearby lot views, live availability, filtering, directions, and a manager dashboard for patterns and misuse review. Out of scope: camera installation, training a new computer-vision model, payments, reservations, and automated enforcement.

Methods used: function points and story points to cost, with a four-person team at 20 project hours per person per week and a 40-hour integration and coordination allowance.

  • Range: 340 to 680 team hours
  • Expected hours (PERT): 538 hours
  • Classroom loaded rate: $60 per person-hour (assumption for this estimate only)
  • Cost range: $20,400 to $40,800; expected about $32,280
  • Calendar: about 4.25 to 8.5 weeks at 80 team hours per week; expected about 6.7 weeks
  • Appendix date: October 5, 2026 (consolidates the September 29 estimate)

Scroll the PDFs below for the Estimation Appendix and the supporting Lesson 9 worksheets. Use Download PDF when you need a copy for review.

Document Estimation Appendix

Sprint 2 Estimation Appendix

Sprint: 2 · Date: October 5, 2026 · Purpose: Consolidated function-point and story-point range for Live Parking Monitoring, ready for the business case and budget.

Download PDF

Document Project Estimation Starter

A first look at project size

Sprint: 2 · Purpose: Supporting worksheet: Release 1 capability list, outside-view experience, and similar-product research used before the slice estimate.

Download PDF

Document Lesson 9 Part 2 Estimation Activity

Estimate one slice of the project

Sprint: 2 · Purpose: Supporting worksheet: dual-method slice estimate, team-size check, and gap explanation that feed the Estimation Appendix.

Download PDF